You acclimatise timber flooring so its moisture content matches the conditions in your home before it’s laid. There’s no fixed number of days. Solid boards are ready when moisture-meter readings show they suit the home, while engineered boards follow the manufacturer’s storage instructions, which can be as short as 48–72 hours for some products.
Get this step wrong and boards can shrink, leaving gaps, or swell, causing cupping and buckling. Thrust Floors has installed timber floors in Sydney homes for more than 50 years, and this guide explains why acclimatisation matters, how long it takes and how to do it properly.
Why You Need to Acclimatise Timber Flooring
Timber is hygroscopic: it takes up moisture from humid air and releases it in dry air. As its moisture content changes, boards swell or shrink across their width. The Australian Timber Flooring Association’s rule of thumb is that every 3% change in moisture content changes a board’s width by about 1%. On a 130mm board, that’s about 1.3mm per board, which adds up quickly across a room.
If the boards are laid at a moisture content very different from the home’s, they keep moving after installation. That’s when problems appear, and it’s why installers acclimatise timber flooring before laying it.
What Happens If You Don’t Acclimatise Timber Flooring?
| If boards are laid too wet | If boards are laid too dry |
|---|---|
| Boards swell after installation | Boards shrink after installation |
| Cupping (edges higher than centres) | Gaps between boards |
| Buckling or lifting, pressure on walls | Squeaks and loose boards |
| Stress on floating floor joints | Coating cracks along joints (site-finished floors) |
Some of these problems can also come from leaks, a damp slab or missing expansion gaps, so acclimatisation is only one part of a stable floor. If you already have gaps, read how to fix gaps between timber floorboards.
How Long Does It Take to Acclimatise Timber Flooring?
There’s no universal number of days to acclimatise timber flooring. What matters is the moisture content, not the time.
- Solid timber: In Australia, flooring is dried to between 9% and 14% moisture content under AS 2796, with an average of about 11%. That suits typical Sydney and Melbourne conditions, so boards delivered to a normal home may need little change. Boards going into very dry or very humid homes need longer, and the installer keeps checking with a moisture meter until the readings are right.
- Engineered timber: Its layered construction makes it far more stable. Most manufacturers specify how long to leave it on site, and often whether to keep it sealed in its packaging. Some products call for 48–72 hours, others for longer. Always follow the product’s installation guide, because ignoring it can void the warranty.
- Parquet blocks: Treat them like solid timber if they’re solid, or follow the guide if they’re engineered.
Read more in solid vs engineered wood.
How Sydney’s Climate Affects Acclimatisation
Sydney isn’t one climate. A beachside home in the Eastern Suburbs, a fully air-conditioned apartment and a house in Western Sydney can have very different indoor humidity. University of Tasmania timber research groups in-service conditions like this:
| Home conditions | Typical timber moisture content | What it means |
|---|---|---|
| Moist (cool and damp, or hot and very humid) | About 12.5–16% | Timber expands; acclimatise and allow extra expansion space |
| Normal | About 10–12.5% | Timber stays relatively stable |
| Dry (air-conditioned, heated, or large north-facing windows) | About 8–10% | Timber shrinks; acclimatise before laying |
Source: University of Tasmania, floor laying seminar notes.
These conditions decide how long you need to acclimatise timber flooring in your home. For most homes, indoor humidity of about 40–60% keeps timber comfortable. Running air conditioning constantly, or closing up a house for long periods, can push conditions outside that range. Learn more in how engineered timber handles Sydney’s humidity.
How to Acclimatise Timber Flooring Properly
Follow these steps to acclimatise timber flooring before installation.
- Get the building ready first. The home should be closed in and weatherproof, with windows and doors fitted. Plastering, painting, tiling and screeds must be dry, because timber will soak up their moisture.
- Check the subfloor. Concrete slabs must be tested and dry. Read why moisture testing a slab matters.
- Run the home as it’ll be lived in. If you’ll use air conditioning or heating, run it before and during acclimatisation.
- Store boards in the room where they’ll be laid. Keep them flat, off the floor and away from direct sun, garages and fresh concrete.
- Let air reach the boards. For solid timber that needs acclimatising, spread the boards out or stack them with spacers. Leaving them in a tight block stack won’t acclimatise each board.
- Follow the product guide for engineered boards. Many should stay sealed until installation.
- Measure and record. The installer checks board moisture readings, room conditions and slab results before laying, and records them.
Acclimatisation Won’t Fix a Damp Subfloor
Acclimatising timber flooring only works if the rest of the site is ready. If a slab is still drying, or a subfloor is damp, boards will take up that moisture after they’re laid, no matter how long they sat in the room. Moisture testing, a suitable moisture barrier and correct expansion gaps all matter as much as acclimatisation. See can timber flooring go over tiles or a concrete slab?
Can You Acclimatise Timber Flooring for Too Long?
Yes, if the conditions are wrong. Boards left for weeks in a damp, unfinished building, or in a hot, closed-up house, will move away from the right moisture content rather than towards it. If your project is delayed, ask your installer whether the flooring should stay sealed, stay on site or go back into controlled storage.
What About Underfloor Heating?
Heated floors need extra care. The heating system usually has to be commissioned and run through a set warm-up sequence before the floor is laid, and only some products are approved for it. Read can engineered timber flooring be used with underfloor heating?
How Acclimatisation Fits Into Your Timeline
Acclimatisation happens after delivery and before laying, so build it into your schedule. Prefinished engineered floors usually need the least time on site. See our timber flooring installation timeline and prefinished vs site-finished timber.
Let Us Acclimatise Timber Flooring the Right Way
We test your subfloor, check board moisture on delivery and record the readings before we lay a single board. Every installation is backed by our 10-year written guarantee. Browse our engineered timber flooring and timber flooring in Sydney, see why homeowners choose us, then request a free measure and quote or call 02 9533 9577.
Frequently Asked Questions
How long should you acclimatise timber flooring?
There’s no fixed time. Solid timber is acclimatised until moisture readings suit the home’s conditions. Engineered timber follows the manufacturer’s guide, which for some products is 48–72 hours. A blanket rule such as “always one week” doesn’t suit every product or home.
Does engineered timber need to acclimatise?
Usually it needs less time than solid timber because its layered core is more stable, but most manufacturers still specify a period on site. Some require the boards to stay sealed in their packaging until installation. Follow the product guide to keep the warranty valid.
What moisture content should timber flooring be?
Under AS 2796, Australian hardwood flooring is supplied at 9–14% moisture content, averaging about 11%. The right figure for your floor depends on your home’s conditions, which is why the installer measures before laying.
Should I open the boxes to acclimatise flooring?
For solid timber that needs acclimatising, yes: boards should be spread out or stacked with spacers so air reaches every face. For engineered flooring, many manufacturers say to keep packs sealed, so check the guide first.
Can I acclimatise timber flooring in the garage?
It’s best not to. Garages are often cooler, damper or hotter than the living areas. Store flooring in the room where it’ll be laid, or in conditions as close to it as possible.
What happens if timber flooring isn’t acclimatised?
Boards that are too wet can swell, cup or buckle after installation. Boards that are too dry can shrink, leaving gaps. Some of these problems also come from damp subfloors or missing expansion gaps.
Does laminate or hybrid flooring need to acclimatise?
Many laminate and hybrid products have their own acclimatisation instructions. Follow the manufacturer’s guide for the product you choose, because requirements differ between brands.
Does air conditioning affect timber flooring?
Yes. Constant refrigerated air conditioning dries the air, which can shrink timber. Run the home as you normally will during acclimatisation, so the boards adjust to real living conditions.