Timber flooring installation usually takes 1–3 working days for a prefinished engineered floor in a room or open-plan area, and about a week for a whole home. Solid timber or parquet that’s sanded and coated on site takes longer, typically 1–2 weeks or more, because the coatings need drying time between coats and about 7 days to fully cure.
Those are installation times on a prepared site. The full project, from measure to moving furniture back, also includes ordering, subfloor checks and preparation. Thrust Floors has installed timber floors across Sydney for more than 50 years, and this guide shows how long each stage takes and what causes delays.
Timber Flooring Installation Time by Floor Type
| Floor type | Typical time to lay (prepared site) | What adds time |
|---|---|---|
| Floating prefinished engineered timber | 1–3 days for a room or living area; several days for a whole home | Door trims, transitions, stairs |
| Direct-stick (glue-down) engineered timber | A little longer than floating | Slab preparation, adhesive cure before heavy furniture |
| Herringbone or chevron parquet | About 3–6 days | Accurate set-out, cutting, borders, sanding and coating if site-finished |
| Solid timber, sanded and coated on site | 1–2 weeks or more in total | Sanding, 2–3 coats, drying and curing time |
| Timber-look hybrid or laminate (floating) | Often 1–2 days for an average area | Levelling, trims |
Indicative times for an average Sydney home with the subfloor ready. Your installer will confirm a schedule after a site measure.
The Stages of Timber Flooring Installation
Stage 1: Measure, quote and product selection
A site measure checks room sizes, subfloor condition, door clearances, stairs and fixed cabinetry. Stocked products can arrive quickly, while special species, wide boards or custom parquet may have longer lead times. Choose your floor early so delivery doesn’t hold up the job. Our guide to the best timber for flooring can help.
Stage 2: Clearing the area and removing old flooring
Furniture and appliances must be moved, and old carpet, tiles or vinyl removed. Removing carpet is quick, while tiles and glued-down floors take longer.
In homes built before 1990, take care with old vinyl, lino and underlay. NSW Government guidance warns that vinyl flooring containing asbestos looks the same as vinyl without it, so get suspect material checked by a licensed assessor before it’s disturbed. Allow time for this in your schedule.
Stage 3: Subfloor checks and preparation
Most delays in timber flooring installation start here. Concrete slabs need moisture testing and may need grinding, levelling or a moisture barrier. Timber subfloors may need loose boards fixed, joists packed or plywood laid. Minor preparation can be done the same day, while levelling compounds and plywood can add a day or more. Read can timber flooring go over tiles or a concrete slab?
Stage 4: Acclimatising the timber
There’s no fixed number of days. Solid timber should be delivered and checked with a moisture meter until its moisture content suits the home, while many engineered products have specific storage instructions. The building should be closed in, with wet trades finished. Learn more in why timber flooring needs to acclimatise.
Stage 5: Laying the floor
This is the timber flooring installation itself. Floating floors click together over an underlay and are the fastest. Glue-down boards take longer because adhesive is spread as the boards are laid. Solid boards are nailed or glued to joists, battens or plywood. Patterned parquet takes the longest per square metre, because every block must follow precise set-out lines.
Stage 6: Sanding and coating (site-finished floors only)
Raw solid timber and site-finished parquet are sanded flat, then given two or three coats. Many water-based floor coatings need about 4 hours between coats and around 7 days to fully cure, and rugs should stay off until the coating has hardened. Prefinished floors skip this stage, which is why they’re so much faster. Compare the two in pre-finished vs site-finished timber flooring.
Stage 7: Trims, skirting and handover
Skirting or scotia, door trims and transitions are fitted, the floor is cleaned and inspected, and you get care instructions. See our five tips to maintain your timber floor.
Example Timelines for Sydney Homes
Here’s how timber flooring installation typically runs in two common Sydney projects.
Prefinished engineered timber, about 50 m² open-plan living area (floating):
- Day 1: Remove carpet, check moisture and prepare the subfloor.
- Days 2–3: Lay the floor, fit trims and transitions, clean up.
- You can usually use the room once the installers finish.
Solid timber, sanded and coated on site, about 80 m² (whole level):
- Week 1: Remove old flooring, prepare the subfloor and lay the boards.
- Week 2: Sand, apply 2–3 coats with drying time between, then fit trims.
- Next 7 days: Light use only while the coating cures. Rugs go down after that.
These examples assume the site is ready and there are no hidden repairs.
What Commonly Delays Timber Flooring Installation?
- High slab moisture or a damp subfloor.
- Uneven floors that need levelling or grinding.
- Unexpected repairs under old flooring, or suspected asbestos.
- Late delivery or a change of product.
- Wet trades, painters or other trades still working in the area.
- Furniture or appliances not cleared.
- Apartment rules, such as lift bookings and limited working hours.
- Complex stairs, borders or layout changes.
When Should Flooring Happen in a Renovation?
Timber flooring installation normally comes after the building is closed in and after dusty and wet work, such as plastering, tiling and plumbing, is finished. Many renovators also do the floor before the final coat of paint, so painters can touch up after skirting is fitted. Kitchens need special planning, because floating floors usually shouldn’t sit under heavy fixed cabinetry. Read flooring before or after kitchen cabinets.
If you’re living in the home, the floor can be laid in stages so you keep access to key rooms. That takes longer on the calendar but causes less disruption.
How to Keep Your Timber Flooring Installation on Schedule
- Choose the floor early and confirm stock or lead times.
- Book a site measure and moisture check before setting dates.
- Clear rooms and agree who removes old flooring, skirting and doors.
- Finish wet and dusty trades first.
- Choose prefinished timber if time matters most. Browse our engineered timber flooring and floating floors.
- Allow cure time before moving heavy furniture onto glued or site-coated floors.
For budgeting, see our timber flooring cost guide.
Book Your Timber Flooring Installation in Sydney
We’ll measure, test your subfloor and give you a clear written schedule before any work starts. Every installation is backed by our 10-year written guarantee. See our timber flooring in Sydney, parquet flooring and why homeowners choose us, then request a free measure and quote or call 02 9533 9577.
Frequently Asked Questions
How long does timber flooring installation take?
On a prepared site, a prefinished engineered floor usually takes 1–3 working days for a room or living area, and about a week for a whole home. Solid timber that’s sanded and coated on site takes 1–2 weeks or more.
How many square metres of timber floor can be laid in a day?
It depends on the floor type, layout and team size. Floating engineered boards in open rooms go down fastest. Glue-down boards, many doorways and patterned parquet are much slower.
How long after installation can I walk on a timber floor?
Prefinished floating floors can usually be walked on straight away. Glue-down floors need the adhesive to cure before heavy furniture goes back. Site-coated floors need drying time between coats and about 7 days to fully cure, so keep rugs off until then.
How long does timber need to acclimatise before installation?
There’s no set number of days. Solid timber should be checked with a moisture meter until it suits the home’s conditions, and engineered products should follow the manufacturer’s storage instructions.
Can I stay in my home during timber flooring installation?
Usually, yes, especially with prefinished floors. With site-finished floors, you’ll need to stay off the floor during sanding and coating, so many people stay elsewhere for a few days or have the work done in stages.
How long does herringbone parquet take to install?
About 3–6 days to lay for a typical area, plus sanding and coating time if it’s finished on site. Accurate set-out and cutting take much longer than straight boards.
Should flooring go in before or after painting?
Most renovators lay the floor before the final coat of paint, so any marks from fitting skirting can be touched up. Protect the floor well if painters work after it’s laid.
What causes the most timber flooring installation delays?
Subfloor problems are the most common, including damp slabs, uneven floors and hidden repairs under old flooring. A site measure and moisture test before you lock in dates avoids most surprises.